DAY 13, Wednesday August 6th


8:30am: The garage roll-up door has been installed. In spite of being 16 x 7 feet and made of
insulated steel, the door rolls so easily Pat can raise and lower it.


4pm: Now the garage is complete, including the electrical work inside and out.
All that's left is to install the opener.


View up the driveway, Garage complete.


"Reference" view


For the record, a shot of where the house electric sub feed and water lines are
(right below where they'll hook to the house).


And the completed electrical panel, neatly labeled and ready for inspection!

<< Back | >> Thursday, August 6th - Saturday, August 9th: R & R